The system, originally installed in 2006, was completely removed and upgraded after a joint assessment in 2021 determined that all 30 modules needed to be replaced.
Danieli reported that the shutdown followed a strict 23-day schedule with 24-hour shifts. The dismantling of the old system was completed in three days, and the installation of new modules in three more, allowing Emsteel to resume full production on September 17.