In the oxygen-converter shop of the Dneprovsky metallurgical plant (DMZ, Dnipro), a major overhaul of the converter No. 1 was carried out with the replacement of the neck and the tapered part.
The renovation took place since December 2020. The workers of the metallurgical equipment repair shop dismantled the old converter neck and installed a new one, which was cast in the molding shop.
During the repair, 3.5 rows of metal structures of the tapered part were replaced, which required the completion of about 120 meters of welding seams.
In March, specialists from the metallurgical furnace repair department joined the process. For 10 days they laid a new masonry. This time, Polish-made bricks were used for lining, the guarantee for these refractories is 2100 heats instead of the standard 1900.
As of today, converter # 1 has been put into operation after overhaul, converters # 2 and # 3 are in reserve.
Subscribe to news

Metallurgy news
- Today
02:00 Insteel reports earnings of $14.6 million for fiscal fourth quarter compared to fourth quarter of 2024 - 16 October 2025
19:00 Eurozone industrial production fell by 1.2 percent in August 2025 compared to July 18:00 PASSAD: Türkiye must increase stainless steel production, import duties will be levied AD 18:00 Sarrall upgrades EAF for Celsa France 17:00 Ukrainian Interpipe reported a decrease in net profit for the first half of 2025 17:00 Fenix Resources iron ore production increased in September due to the commissioning of Beebyn-W11 17:00 Are you paying for real work or for imitation activities? 16:00 Japan's domestic steel consumption fell 2.1 percent in January-August 2025
Publications
16.10 The most popular MFOs in Kazakhstan 16.10 Beyond the Horizon: The Most Breathtaking Boating Destinations on Earth 14.10 The best fonts in design: how to choose and where to use 13.10 Sales funnel: the key to understanding customer behavior 13.10 Portal of banking and microfinance products